Turnkey delivery

From the port to your slab: 8-12 weeks

Integrated logistics: sea freight from the factory in China, customs clearance, road delivery, crane-truck unloading, connection, commissioning. A single team coordinates it all, and you follow the schedule.

Typical timeline

8 to 12 weeks, from purchase order to commissioning

  1. J+0OrderSignature, deposit, confirmed schedule
  2. S1-S4ManufacturingPanels, cooling unit, factory inspection
  3. S5-S8Sea freightTransit from China to EU port
  4. S9CustomsImport formalities and port clearance
  5. S10-S12InstallationCrane truck, connection, commissioning

The typical schedule

  1. 1

    Signature + 50% deposit

    Pivot date: the clock starts here. You receive a detailed projected schedule.

  2. 2

    Weeks 1-4: factory production

    Production in China to your configuration (panels, unit, options). Quality control at the factory exit, photos sent to the customer.

  3. 3

    Weeks 5-8: sea freight

    Loading at the Chinese port, transit to Le Havre or Fos-sur-Mer (4-5 weeks depending on the route). Container tracking available.

  4. 4

    Week 9: customs clearance

    EU and UK import formalities: customs declaration, port unloading, safety and compliance checks. Handled by CGGK — UK orders are delivered duty paid (DDP), so import duties and clearance are taken care of for you.

  5. 5

    Weeks 10-11: road delivery

    Specialist crane truck handles unloading. Five business days' notice before the date. Sited on your prepared slab or footings.

  6. 6

    Week 12: commissioning

    R290 pre-charged models: start-up on your own following the guide. Uncharged models: partner Cat. I refrigeration engineer (2-5 days after delivery) for charging + start-up.

Site preparation — your checklist

  • Concrete slab or footings: poured and cured for at least 28 days before delivery (full concrete curing)
  • Crane-truck access: width ≥ 3.5 m, clear height ≥ 4.5 m, load-bearing ground
  • Electrical connection: board ready, rating confirmed, 30 mA RCD
  • Defrost water drainage: connection to the waste network or a sealed tank nearby
  • Someone on site: one point of contact available on delivery day to take receipt + sign
  • Refrigeration engineer contacted (if delivered uncharged): we coordinate, but you remain the final point of contact

A specific project? Quote within 48 hours.

Tell us your use case, target volume and delivery address. Our technical team replies with a sized specification and a clear ex-VAT price within two business days.