From the port to your slab: 8-12 weeks
Integrated logistics: sea freight from the factory in China, customs clearance, road delivery, crane-truck unloading, connection, commissioning. A single team coordinates it all, and you follow the schedule.
8 to 12 weeks, from purchase order to commissioning
- J+0OrderSignature, deposit, confirmed schedule
- S1-S4ManufacturingPanels, cooling unit, factory inspection
- S5-S8Sea freightTransit from China to EU port
- S9CustomsImport formalities and port clearance
- S10-S12InstallationCrane truck, connection, commissioning
The typical schedule
- 1
Signature + 50% deposit
Pivot date: the clock starts here. You receive a detailed projected schedule.
- 2
Weeks 1-4: factory production
Production in China to your configuration (panels, unit, options). Quality control at the factory exit, photos sent to the customer.
- 3
Weeks 5-8: sea freight
Loading at the Chinese port, transit to Le Havre or Fos-sur-Mer (4-5 weeks depending on the route). Container tracking available.
- 4
Week 9: customs clearance
EU and UK import formalities: customs declaration, port unloading, safety and compliance checks. Handled by CGGK — UK orders are delivered duty paid (DDP), so import duties and clearance are taken care of for you.
- 5
Weeks 10-11: road delivery
Specialist crane truck handles unloading. Five business days' notice before the date. Sited on your prepared slab or footings.
- 6
Week 12: commissioning
R290 pre-charged models: start-up on your own following the guide. Uncharged models: partner Cat. I refrigeration engineer (2-5 days after delivery) for charging + start-up.
Site preparation — your checklist
- Concrete slab or footings: poured and cured for at least 28 days before delivery (full concrete curing)
- Crane-truck access: width ≥ 3.5 m, clear height ≥ 4.5 m, load-bearing ground
- Electrical connection: board ready, rating confirmed, 30 mA RCD
- Defrost water drainage: connection to the waste network or a sealed tank nearby
- Someone on site: one point of contact available on delivery day to take receipt + sign
- Refrigeration engineer contacted (if delivered uncharged): we coordinate, but you remain the final point of contact